Friday, 24 October 2014

Framing Update

Most of the framing was completed by end of Thursday.  Jason mentioned the roof trusses would likely be delivered on Friday, ready for lifting with crane on Monday.  They are also waiting on a supply of wall studs for the garage, as there was not sufficient amounts supplied for the job.

My father-in-law and I gave the carpenters a hand to lift the alfresco laminated and solid timber beams into place as they were incredibly heavy!

Framing from front of property - garage still to be framed

Is there a secret doorway between the two bedrooms?

Hallway - all frame work is straight as an arrow!

Alfresco and kitchen/living

Frame from rear of property

1 comment:

  1. Wow. It sure is moving on. It must be nice to start feeling a sense of space when you you walk around.

    ReplyDelete