Early the following Monday saw a large concrete pump being set up at our block. We visited the site and the concrete crew were well into the pour, with three concrete trunks queued on our street, ready to pour.
Things progressed well, with the team finishing around 4pm. All up, 10 trucks & approx 95 cu meters of concrete.
No comments:
Post a Comment