Thursday, 29 January 2015
Tuesday, 27 January 2015
Data and home automation cabling
Cabling for home automation, data and A/V commenced on Wednesday. The team worked really well running cables. The preparation we spent over Christmas/New Year period installing wall plates (with labels for each cable), catenary system between key cable paths, noggins/studs and conduits for cable segregation and mounting plates also helped make the process progress smoothly. A big thanks to Ian as well for the detailed diagrams.
Work completed involved:
Work completed involved:
- C-Bus cabling (pink cables)
- A/V cabling (speakers, HDMI, RCA, antenna)
- Ethernet cabling
- Automation and security cabling
| Lounge TV area cabling |
| Catenary system to rear of house |
| Data cabling to A/V of living room |
| Pink C-Bus cable in toilet (markings for lighting can be seen on floor behind) |
Wednesday, 21 January 2015
First fix electrical
| GPO's for down light connection |
| GPO's for down light connection |
| Wall plates for power points |
Friday, 12 December 2014
Monday, 1 December 2014
Home automation and data cabling structural work
A few pictures of work we conducted to install the structural work for C-Bus, home automation and security system.
Plenty of work still to be done, including C-Bus bracket locations, living room cabinet services and finally cabling mid January 2015.
Plenty of work still to be done, including C-Bus bracket locations, living room cabinet services and finally cabling mid January 2015.
| Home theatre room conduit and wall plates |
| Wood trim for home automation cabinets with machined top plates for cable entry |
| Wood trim for C-Bus cabinet, with main service for each cabinet in conduit |
| Bedroom 1 |
| Activity room with data services for TV |
| Main living room with conduit for data services to TV |
Monday, 24 November 2014
Bricks
Bricking started on Tuesday last week, but have had a few days of rainy weather. A few progress pics...
Brick layers said the job would be finished in 3-4 weeks. The front of the house has 'seconds' bricks that will be rendered in Surfmist later. Rest of the house has Vanilla Ice bricks from PGH with rolled grey mortar joints.
Brick layers said the job would be finished in 3-4 weeks. The front of the house has 'seconds' bricks that will be rendered in Surfmist later. Rest of the house has Vanilla Ice bricks from PGH with rolled grey mortar joints.
| Vanilla Ice bricks for remaining house. Clamps for defining area with articulation joints. |
| Bricks to be rendered |
| Inside master bedroom at end of Monday |
| Finished bricking front of bedroom 1 - bricks to be rendered |