Monday, 1 December 2014

Bricks update

Electricity and gas meter boxes 

Progress to south west wall of house

Detail for perimeter Termimesh on first course of bricks



Monday, 24 November 2014

Bricks

Bricking started on Tuesday last week, but have had a few days of rainy weather.  A few progress pics...

Brick layers said the job would be finished in 3-4 weeks.  The front of the house has 'seconds' bricks that will be rendered in Surfmist later.  Rest of the house has Vanilla Ice bricks from PGH with rolled grey mortar joints.

Vanilla Ice bricks for remaining house.  Clamps for defining area with articulation joints.

Bricks to be rendered

Inside master bedroom at end of Monday

Finished bricking front of bedroom 1 - bricks to be rendered

Sunday, 16 November 2014

Roof complete

The roof team finished on Friday.  A few pics of the completed work.  Unusually, some sarking was added to the eastern and western sides (above windows).  I'm not sure whether this is for building code, as we had not specified any sarking with the build.

Also, a call with the site supervisor on Friday and he mentioned bricking will start early this week.

Roof trusses with tiles

Close up detail of tile colour/texture and mortar

Roof tiles from back

Roof tiles over alfresco

Front of house


Tuesday, 11 November 2014

Gutter/fascia completion and roof tiles update

The fascia was completed early Monday with scaffolding also installed.  The roof tilers were onsite today.  Most of the eastern side was covered by end of day!

Some good weather expected for the rest of the week - and then rain expected on Friday.  Will be nice to have a roof!

Tiles over garage

Tiles from rear of property

Tiles at roof level

Tiles on site boundary

Tile elevator


Friday, 7 November 2014

Water installation and roof tile delivery

Lots of tiles stacked at the front of our property.  Our site supervisor mentioned they would be installed next week.  Further progress made on the fascia gutters.

Lots of plumbing work complete, with the house left pressurised.

Lots of water in this wall!

Water for instant gas hot water (recessed box)

Back inlet for toilet (green pipe for rainwater)

One of the external taps for irrigation


Island bench services

Tiles ready for installation

Tiles ready for installation



Thursday, 6 November 2014

Window/external door frame installation, frame completion & fascia/gutters stated

Another big day on site:

  • all windows installed
  • front door frame (and glass)
  • hall-way door frame (and glass)
  • frame completed
  • fascia/gutters stated
Thanks again to the carpenters Jason and Steve - they definitely take pride in their work and it shows in the finished product!

Front door frame and glass

Hallway door frame

Windows and doors installed in living area / kitchen (click picture for a larger version)

Front of house with windows and door frame


Tuesday, 4 November 2014

Frame update, window delivery and perimeter Termimesh

A big last few days with most of the framing complete, a delivery of our windows, sliding doors and exterior door frames and installation of Termimesh perimeter protection.


Termimesh perimeter stainless mesh ready for first course of bricks


Installation of the living area/hallway cavity sliding door

Rear of property with almost complete roof structure

Lachie looking at our front door frame


Windows and door frames

Windows and sliding doors

Sliding door handles


Framing update from bedroom 1

Framing update

Gas fitter set up to fit pipes

Gas entry for oven